214 Oak Ave
Tue, Nov 3
Clear41–56°F
Wind 6 mph
Rain 0.00 in
Rain 0.00 in
Tue, Nov 3
Bexley, OH
Bexley, OH
Crew3 on site, 21.5 h
| Marco Reyes | 7:30–4:00 | 8 h |
| Tyler Brandt | 7:30–4:00 | 8 h |
| Luis Ortega | 10:00–4:00 | 5.5 h |
Work done2 subs on site
- Finished hanging the upper cabinets on the north wall
- Started framing the mudroom bench
- Ran the under-cabinet lighting (Kessler Electric, 2)
Inspections
Rough electrical, 1:15
Issues1 open
The 36 inch sink base came in damaged, supplier is sending a new one Friday