Skip to contentJobs
2 of 4 jobs need you today: 87 Linden St (no note yet) and 12 Maple Ct (held for footing inspection).
Write today’s notes| Job | Progress | Today | On site | Open issues | Next |
|---|
| 214 Oak AveKitchen + mudroom remodel, Jen & Sam Parker | Week 6 of 11 | Logged 4:12 pmLead: Marco Reyes | 3 crew 2 subs | 1 | Countertop template, Mon 11/9 |
| 87 Linden StPrimary bath remodel, Ruth Okafor | Week 3 of 6 | No note yetLead: Jo Bergstrom | 2 crew 1 subs | 0 | Shower pan flood test, Wed 11/4Write the note |
| 12 Maple CtDeck rebuild + screened porch, Tom Weiss | Week 4 of 5 | Held for footing inspectionLead: Andre Willis | 0 crew | 2 | Footing inspection, Thu 11/5, 9:00 am |
| 3306 Ashby RdBasement finish, Priya Nair | Week 8 of 9 | Logged 3:40 pmLead: Tyler Brandt | 2 crew | 0 | Final electrical, Mon 11/9 |
214 Oak AveLogged 4:12 pm
Kitchen + mudroom remodel. Week 6 of 11. 3 crew, 2 subs. 1 open issue.
Next: Countertop template, Mon 11/9
87 Linden StNo note yet
Primary bath remodel. Week 3 of 6. 2 crew, 1 subs. 0 open issues.
Next: Shower pan flood test, Wed 11/4
12 Maple CtHeld for footing inspection
Deck rebuild + screened porch. Week 4 of 5. 0 crew, 0 subs. 2 open issues.
Next: Footing inspection, Thu 11/5, 9:00 am
3306 Ashby RdLogged 3:40 pm
Basement finish. Week 8 of 9. 2 crew, 0 subs. 0 open issues.
Next: Final electrical, Mon 11/9