Dear Jen and Sam,
Drywall is finished in the kitchen and mudroom, and every wall is primed. Tuesday’s rain cost us nothing because all the work is inside now. The mudroom floor tile is set and grouted, and your cabinets arrive Monday morning.
Marco Reyes, lead carpenter
The week on site
Done this week
- MonFramed the mudroom bench base
- MonCut the window stool and apron
- MonFinal coat and sanding (Fultz Drywall)
- TuePrimed kitchen and mudroom walls and ceilings
- TueInstalled window trim
- WedLeveled the floor at the old wall line
- WedCement board down in the mudroom
- WedMeasured backsplash and mudroom floor (Bexley Tile & Stone)
- ThuDumpster swapped
- ThuSnapped cabinet layout lines
- ThuSet the mudroom floor tile (Bexley Tile & Stone)
- FriFirst coat of wall paint
- FriStaged the garage for cabinet delivery
- FriGrouted the mudroom floor (Bexley Tile & Stone)
Coming next week
- Mon–Wed: hang the upper and base cabinets
- Tue: under-cabinet lighting and the rough electrical inspection
- Thu–Fri: build the mudroom bench, finish paint
- Mon 11/9: countertop template with Bexley Tile & Stone
What we need from you
- Pick the mudroom bench cushion fabric by Wed 11/4
- Confirm pendant height over the island. We suggest 32 in above the counter. by Fri 11/6